(Українська) Mountain Residence Tower III - звіт з будівництва за грудень

Video report for November

For your attention, a video report on construction for November 2022.
As of December 3, 2022:
The entrance to the facility is asphalted.
5 foundation slabs have been formed.
Columns and walls of the first floor of the parking lot have been formed.
Preparatory work formed on the sixth (last) foundation slab has begun.
Preparatory work is being carried out for the pouring of the floor slab of the first floor, slabs No. 6 and No. 5

Construction video report

The most relevant from construction

Mountain Residence Tower III

Video report for October 2022

Mountain Residence Tower III is under construction
For your attention, a video report on construction for October 2022.
As of November 2, 2022:
The 2nd and 3rd foundation slabs have been formed.
The pouring of 4 foundation slabs is in progress.
The columns and walls of the parking lot have been formed.
The foundation of the road to the object has been made.
The soil was stabilized and a gravel layer of the road was created. 
Electrical cables have been laid to the object.

September 2022 video report

Publicly available
Mountain Residence Tower III
Construction is ongoing
As of October 2, 2022:
Soil sampling has been completed throughout the building area.
The first part of the foundation slab is poured.
Preparatory work on pouring the 2nd and 3rd parts of the foundation slab is in progress.

Video report for August 2022

The following works were carried out:

Land works were carried out to remove soil and prepare the area for pouring the foundation.

Video report for July

The following works were carried out:

1. Preparation of the land plot
2. Geology and geodesy were carried out
3. Project documentation has been approved
4. 800 meters of a new road branch to the complex was built
5. Work on the construction of the pit has begun